How Long Does a Kitchen Renovation Take in Ontario? A Realistic Timeline

The first question every homeowner asks before starting a kitchen renovation isn’t about countertops or cabinet colors. It’s: “How long will I be without a kitchen?”

 

The honest answer depends on the scope of your project, your cabinet type, and how well the job is coordinated. A simple cabinet swap can be done in days. A full gut renovation with layout changes can take months.

 

As professional cabinet installers working across Southwestern Ontario and the GTA, we’ve been part of hundreds of kitchen renovations. This guide breaks down the realistic timeline for each phase, what causes delays, and how to avoid them.

 

Quick Answer: Kitchen Renovation Timelines by Project Type

Project Type

 

 

Total Timeline

 

 

Kitchen Downtime

 

 

Cabinet refacing only

 

 

3–5 days

 

 

1–2 days

 

 

IKEA/RTA cabinet install (same layout)

 

 

1–3 weeks

 

 

5–10 days

 

 

Custom cabinet install (same layout)

 

 

6–12 weeks

 

 

2–3 weeks

 

 

Full gut renovation (layout change)

 

 

10–16 weeks

 

 

4–8 weeks

 

 

Full gut with structural changes

 

 

16–24 weeks

 

 

8–12 weeks

 

 

 

Important: “Total timeline” includes ordering, manufacturing, and lead times. “Kitchen downtime” is the period your kitchen is non-functional.

 

Phase 1: Planning and Design (1–4 Weeks)

Before any demolition happens, you need a plan. This phase includes:
  • Initial consultations with designers or contractors
  • Measuring the space (critical for cabinet orders)
  • Selecting cabinet style, countertop material, backsplash, hardware, appliances
  • Finalizing the layout and getting a detailed quote
  • Applying for permits (if structural changes are involved)

How Long This Actually Takes

If you’re decisive: 1–2 weeks. You know what you want, you’ve done your research, and you can make material selections quickly.

 

If you’re still exploring: 3–4 weeks. Multiple consultations, showroom visits, and back-and-forth on design choices.

Common Delay

Indecision on materials. Every time you change your countertop choice or cabinet door style after the order is placed, the timeline resets.

 

Phase 2: Ordering and Manufacturing (1–12 Weeks)

This is the phase most homeowners underestimate. Nothing is happening in your kitchen yet, but the clock is ticking.

 

Cabinet Type

 

 

Typical Lead Time

 

 

IKEA SEKTION (in-stock)

 

 

1–7 days

 

 

IKEA SEKTION (out-of-stock items)

 

 

2–6 weeks

 

 

RTA cabinets (online order)

 

 

1–3 weeks

 

 

Semi-custom cabinets

 

 

4–8 weeks

 

 

Fully custom millwork

 

 

8–12 weeks

 

 

 

Countertops add additional time: quartz and granite fabrication typically requires 2–3 weeks after templating (which can only happen after cabinets are installed).

Common Delay

IKEA stock issues. Specific SEKTION components (corner cabinets, certain door fronts) go in and out of stock unpredictably. We’ve seen projects delayed 3–4 weeks waiting for a single cabinet box. Always check stock before committing to a timeline.

 

Phase 3: Demolition and Prep Work (2–5 Days)

Once materials arrive, the active work begins:
  • Removal of existing cabinets, countertops, backsplash
  • Disconnection of plumbing and electrical
  • Removal of flooring (if being replaced)
  • Drywall repair and patching
  • Addressing any hidden issues (water damage, mold, outdated wiring)

How Long This Actually Takes

Simple removal (same layout, no surprises): 1–2 days

 

Complex removal (layout change, old plaster walls, hidden damage): 3–5 days

Common Delay

Hidden problems. You won’t know what’s behind your cabinets until they come off the wall. In older Ontario homes (pre-1980s), expect the possibility of: outdated electrical not to code, plumbing that needs updating, water damage from decades of slow leaks, or asbestos in older drywall compound.

 

Phase 4: Rough-In Work (3–7 Days)

If your layout is changing, or if demo revealed issues, trades need to come in before cabinets go up:
  • Electrical: Moving outlets, adding under-cabinet lighting circuits, relocating switches
  • Plumbing: Moving sink location, adding dishwasher line, gas line for range
  • HVAC: Adjusting vents if cabinet layout changes
  • Drywall: Patching, replacing damaged sections, preparing mounting surfaces

How Long This Actually Takes

Same layout, minor updates: 1–2 days (or sometimes zero if nothing needs changing)

 

Layout change with multiple trades: 5–7 days including inspection wait times

Common Delay

Permit inspections. In Ontario, electrical and plumbing changes typically require inspection before walls are closed up. Inspection scheduling in the GTA can add 3–5 business days of waiting.

 

Phase 5: Cabinet Installation (1–5 Days)

This is where we come in. Cabinet installation is the structural backbone of the entire kitchen:
  • Installing suspension rail (IKEA) or direct mounting (custom)
  • Leveling and securing base cabinets
  • Mounting upper/wall cabinets
  • Installing filler panels, cover panels, toe kicks
  • Adjusting doors and drawer fronts
  • Installing interior hardware (pull-outs, lazy susans, organizers)

How Long This Actually Takes

Kitchen Size

 

 

IKEA/RTA Install

 

 

Custom Millwork Install

 

 

Small (galley, L-shape, up to 10 cabinets)

 

 

1–2 days

 

 

1–2 days

 

 

Medium (L/U-shape, 10–20 cabinets)

 

 

2–3 days

 

 

2–3 days

 

 

Large (U-shape with island, 20+ cabinets)

 

 

3–5 days

 

 

3–5 days

 

 

Common Delay

Missing or damaged parts. IKEA deliveries frequently arrive with missing components or damaged panels. We always recommend homeowners inventory every single item before scheduling installation day. One missing rail bracket can halt a full day of work.

 

Phase 6: Countertop Fabrication and Installation (2–4 Weeks)

Countertops cannot be templated until cabinets are fully installed and level. The sequence is:

 

  1. Templating (1 day): Fabricator measures the installed cabinets using laser or physical templates
  2. Fabrication (10–15 business days): Cutting, edging, polishing the stone or quartz
  3. Installation (1 day): Setting and securing the countertop, cutting sink hole, sealing

How Long This Actually Takes

Quartz or granite: 2–3 weeks from template to install

 

Laminate: 1–2 weeks (faster fabrication)

 

Butcher block: Can often be installed same week as cabinets

Common Delay

Fabrication backlog. During spring and summer (peak renovation season in Ontario), countertop fabricators often have 3–4 week lead times instead of the usual 2 weeks.

 

Phase 7: Finishing Touches (2–5 Days)

The final phase brings everything together:
  • Backsplash installation (tile, 1–2 days)
  • Plumbing connections (sink, faucet, dishwasher)
  • Electrical connections (range hood, under-cabinet lighting)
  • Appliance installation
  • Hardware installation
  • Touch-up paint, caulking, trim
  • Final cleaning

How Long This Actually Takes

If well-coordinated: 2–3 days with multiple trades working in sequence

 

If poorly scheduled: 1–2 weeks of individual tradespeople coming on separate days

 

Total Realistic Timelines: Three Common Scenarios

Scenario 1: IKEA Kitchen, Same Layout

Phase

 

 

Duration

 

 

Planning & Design

 

 

1–2 weeks

 

 

Ordering (IKEA pickup/delivery)

 

 

1–2 weeks

 

 

Demo & Prep

 

 

1–2 days

 

 

Cabinet Installation

 

 

2–3 days

 

 

Countertop (template to install)

 

 

2–3 weeks

 

 

Finishing

 

 

2–3 days

 

 

Total

 

 

5–8 weeks

 

 

Kitchen Downtime

 

 

7–14 days

 

 

Scenario 2: Semi-Custom Cabinets, Same Layout

Phase

 

 

Duration

 

 

Planning & Design

 

 

2–3 weeks

 

 

Manufacturing

 

 

4–8 weeks

 

 

Demo & Prep

 

 

2–3 days

 

 

Cabinet Installation

 

 

2–3 days

 

 

Countertop (template to install)

 

 

2–3 weeks

 

 

Finishing

 

 

3–5 days

 

 

Total

 

 

10–16 weeks

 

 

Kitchen Downtime

 

 

2–3 weeks

 

 

Scenario 3: Full Custom, Layout Change

Phase

 

 

Duration

 

 

Planning & Design

 

 

3–4 weeks

 

 

Manufacturing

 

 

8–12 weeks

 

 

Demo & Prep

 

 

3–5 days

 

 

Rough-in (electrical, plumbing)

 

 

5–7 days

 

 

Inspections

 

 

3–5 days wait

 

 

Cabinet Installation

 

 

3–5 days

 

 

Countertop (template to install)

 

 

2–4 weeks

 

 

Finishing

 

 

5–7 days

 

 

Total

 

 

16–24 weeks

 

 

Kitchen Downtime

 

 

5–8 weeks

 

 

 

The 5 Biggest Causes of Kitchen Renovation Delays in Ontario

1. Permit and Inspection Wait Times

GTA municipalities (Toronto, Mississauga, Brampton, Hamilton) have varying permit processing times. Budget 2–4 weeks for permit approval if structural, electrical, or plumbing changes are involved.

2. Material Back-Orders

Whether it’s IKEA stock issues, imported stone delays, or custom door manufacturing backlogs, material availability is the number one cause of timeline overruns. Always confirm stock and lead times before committing to a start date.

3. Hidden Structural Issues

Water damage, mold, knob-and-tube wiring, and outdated plumbing are common in Ontario homes built before 1980. These discoveries add 1–2 weeks minimum.

4. Poor Trade Coordination

A kitchen renovation involves 5–8 different trades (demo, electrical, plumbing, cabinet install, countertop, tile, paint, appliance). If these aren’t scheduled in the correct sequence, you get dead days with no progress.

5. Homeowner Decision Changes

Changing cabinet door style after ordering, switching countertop material after templating, or adding scope mid-project are guaranteed timeline extenders.

 

How to Keep Your Renovation on Schedule

  1. Make all material selections before demo day. Every door style, handle, countertop edge, backsplash tile, and paint color should be finalized.
  2. Order materials early. Don’t wait for demo to order cabinets. Have everything on-site before the first hammer swings.
  3. Inventory IKEA deliveries immediately. Open every box, count every piece, check for damage. Report missing items the same day.
  4. Book trades in advance. Countertop templaters, electricians, and plumbers should be booked 2–3 weeks ahead of when you’ll need them.
  5. Build in buffer time. Add 1 week to whatever timeline you’re given. If everything goes perfectly, you finish early. If something goes wrong, you’re still on track.
  6. Set up a temporary kitchen. A folding table, microwave, electric kettle, and access to a bathroom sink can make weeks without a kitchen survivable.

 

When Is the Best Time to Renovate a Kitchen in Ontario?

Season

 

 

Pros

 

 

Cons

 

 

Winter (Jan–Mar)

 

 

Contractors less busy, faster scheduling

 

 

Cold weather complicates deliveries

 

 

Spring (Apr–Jun)

 

 

Weather improves, good for ventilation

 

 

Peak season begins, longer lead times

 

 

Summer (Jul–Sep)

 

 

Ideal for ventilation during paint/adhesive work

 

 

Peak demand, hardest to book trades

 

 

Fall (Oct–Dec)

 

 

Demand drops, better pricing possible

 

 

Holiday season interruptions

 

 

 

Pro tip: If you want the shortest overall timeline, start planning in October/November and begin demo in January. You’ll benefit from faster trade availability and shorter manufacturing queues.

 

The Bottom Line

A kitchen renovation in Ontario realistically takes 5–24 weeks depending on scope. The biggest variable isn’t the physical installation work (which takes days), but the lead times for materials and the coordination between trades.

 

At Blueprint Master, we handle the cabinet installation phase with precision and speed. Our laser-leveled, fully insured process means cabinets go up correctly the first time, keeping the rest of your renovation on schedule. Whether you’re installing IKEA SEKTION, RTA, or custom millwork, we arrive prepared, on time, and finish on spec.